Mẫu phân công lịch trình công trình xây dựng Schedule of CW Pipe Underpass VA1 Facility (80m)
Mẫu phân công lịch trình công trình xây dựng
Schedule of CW Pipe Underpass VA1 Facility (80m)
- Construction work start April 1st, 2023
Schedule of CW Pipe Underpass VA1 Facility
- Start temporary work 1st Dec. 2022
- No.5 : Jet gouting, excavation work for Launch Shaft, Receiving Shaft within 90days
- Start site construction work 1st April. 2023
- No.8 : Concrete wall, slab at Launch Shaft, Receiving Shaft, install TBM machine 30days
- No.9 ~ No.12 : TBM work for each 80m, 40days
- No.13 : Preparation of GRP Pipe installation 30days
- No.14 ~ No.17 : GRP install and joint work for each 80m, 60days (15 joint, 4days/joint)
- No.18 : Grouting between con'c pipe & GRP pipe for 80m, 20days
- No.19 : Backfill by sand and concrete block for Launch Shaft, Receiving Shaft 60days
- No.20 : concrete slab for outside Launch Shaft, Receiving Shaft and joint at T.P 30days
- No.21 : Hand over civil work and mach.work 20day
Xem thêm: METHOD STATEMENT FOR CW PINELINE UNDERPASS VA1 FACILITY
- Tư vấn lập dự án xin chủ trương
- Tư vấn lập dự án kêu gọi đầu tư
- Lập và đánh giá sơ bộ ĐTM cho dự án
- Thiết kế quy hoạch chi tiết tỷ lệ 1/500
- Biện pháp thi công khoan ống
+ Báo cáo Công tác bảo vệ Môi trường.
+ Báo cáo Đánh giá tác động Môi trường ĐTM.
Tại sao nên chọn Công ty CP Tư vấn Đầu tư & Thiết kế Xây dựng Minh Phương ?
Với đội ngũ nhân viên đầy nhiệt huyết, năng lực, và giàu kinh nghiệm.
Là Đơn vị chuyên tư vấn và nhận thầu các dự án đầu tư và thiết kế xây dựng trên Toàn Quốc.
Tư vấn nhiệt tình, giá cả hợp lí, mang tính cạnh tranh cao.
Quy trình làm việc đảm bảo tiến độ nhanh chóng, hiệu quả cao nhất:
Chất lượng dịch vụ được khách hàng tin tưởng và ưu tiên đặt khách hàng lên hàng đầu.
Triển khai thực hiện ngay khi khách hàng kí hợp đồng.
Đảm bảo đúng tiến độ hoàn thành dự án.